Stadium Renovation Project Timetable Report
"First Half" Renovation Timeline
Dates subject to change
Start Date | Task | Completed? |
---|---|---|
Sept. 16, 2024 | Project begins / Site preparation | X |
October 2, 2024 | Groundbreaking Ceremony ("Kickoff") | X |
October 3, 2024 | Scrape grass field, demolish bleachers & light towers | X |
October 9, 2024 | Excavation, installation of drainage system and tank | X |
October 21, 2024 | Pour foundations for new bleachers | |
November 18, 2024 | Install new bleachers and press box | |
November 26, 2024 | Pour new sidewalks | |
December 2, 2024 | Install scoreboard | |
December 6, 2024 | Install foundations for light towers | |
December 6, 2024 | Asphalt paving (weather permitting) | |
December 10, 2024 | Assemble and erect LED lights & towers | |
Late December, 2024 | Synthetic turf installation | |
December 30, 2024 | Fencing and gates | |
January 13, 2025 | Set goalposts | |
January 30, 2025 | Install new electrical wiring | |
Winter Hiatus | ||
April 1, 2025 | Landscaping | |
TBD | Ribbon cutting Ceremony for “First Half” Renovation (“Halftime” of full project) |
“Second Half” Renovation to come: Demolition of concrete grandstand, construction of new fieldhouse
with locker rooms, training and weight rooms, officials’ room, storage, and Large Group Instruction
room; new stadium entrance, concessions and restroom facilities.